May Progress at a Glance

Picture2.png
Picture4.png
Picture3.png
Picture1.jpg

May Summary

  • Finished installation of gymnasium CMU

  • Completed all slab on grade placements

  • Installed two of three stairs in buildings B and A1

  • Started exterior brick on building C

  • Continuing fireproofing and roofing throughout building

1 Month Look Ahead

  • Continue MEPFP rough in buildings C 1st  floor and B 2nd floor

  • Install last stair in A2

  • Install mechanical roof curbs throughout the building

  • Continue exterior brick on building C and B building

  • Interior and exterior framing of B and A1

Upcoming SBC/PBC Meeting

July 14, 2026: SBC/PBC Meeting

Meeting Link: 

https://us06web.zoom.us/j/83939954911?pwd=HaCwPfAY4QHmbe4biPWUO20Q8SV4no.1

​​​Meeting ID: â€‹

839 3995 4911

Passcode: â€‹

136994

One tap: 

+16469313860,,83939954911#,,,,*136994# US

​

Quick Insights

MSBA-BLANCO.png
Sello de la ciudad de Clinton.png
Logotipo DW - Logotipo combinado de colores - cuadrado.png
LPAA.png
Fontaine_edited.jpg
  • Facebook
  • Twitter
  • YouTube

© 2022 Clinton Public Schools

El sitio web tiene como objetivo proporcionar información relacionada con el proyecto de construcción de la escuela secundaria Clinton.

bottom of page